Pathway: Operations > Resource Scheduling > Resource Calendar

Resource Calendar provides a high-level view of worker availability/capability, route statuses and availability conflicts for workers across all routes. In addition, this tool also includes functionality to edit route records and access the Worker Calendar to add availability exceptions as needed. Information displayed in the Resource Calendar is gathered from Worker Availability and Capability, Worker Calendar and Dispatch tools. Review the Logic section below for critical setup requirements before using the tool.

Logic

Permissions

  1. Permission 440 (Resource Scheduling) is required to view and edit the Resource Calendar screen.

  2. Workers must be assigned ONE of the following permissions to display on the Resource Calendar screen:

    • Driver = permission 305

    • Helper = permission 328

    • Crew Member / Laborer / Technician = permission 313

...

...

Filters

Use any of the filtering options provided to limit what displays on the screen. Filters apply to both the Worker grid and Truck grid.

Filter

Description

Worker Assignment Type

Use the Work Assignment Type filter to filter the screen to a specific worker type. Options include:

  • Driver

  • Helper

  • Technician

  • Truck (Future release)

Note

Correct permission setup for workers is critical for filter functionality. Refer to the Logic section above for additional information.

Division

Filters to only display workers of the selected Division.

Line Of Business

Filters to only display workers of the selected Line of Business.

Week

Provides the ability to navigate and view past and future weeks. By default, the current week is displayed.

Understanding the Worker Grid

...

Item

Description

Worker

Workers display vertically along the left side of the screen along with their servicing capabilities. Availability is columned by day of week beginning with Sunday and ending with Saturday.

Access the Worker Calendar

Select the worker’s name to open the Worker Calendar. Add an Availability Exception by right-clicking on the day the exception applies and selecting ‘Add Availability Exception.’

Available vs Not Available

Worker availability is indicated using white and gray cell colors. Days a worker is available display white and include the time frame the worker is available to be scheduled within. Cells for days a worker is not available display gray.

Route Information

Route information displays for the worker on the day the route is scheduled. A red exclamation mark displays by the route if the route is assigned to a worker on a day they are not available or have an availability exception. Select the route to open the Edit Route Record and assign the route to another available resource.

Color Legend

  • Cells

    • Red - indicates the worker has an availability exception (sick, vacation, etc.) for a day they are considered available. Any assignments that day must be re-assigned to a new resource.

    • White - indicates the worker is available to be scheduled for that day.

    • Gray - indicates the worker is not available to be scheduled for that day.

  • Routes

    • Blue - indicates the route is Scheduled.

    • Yellow - indicates the route is In Progress.

    • Green - indicates the route is Serviced.

Re-assign Drivers and Helpers

Click the route to open the Edit Route Record popup editor to reassign resources. Save when finished.

Worker Availability Exceptions

Click on the exception for the worker to open the Edit Worker Availability Exceptions popup editor.

Understanding the Truck Grid

The Resource Calendar consists of two expand and collapse sections: Worker and Truck. The following descriptions apply to the Truck section of the grid.

...

Item

Description

Truck

Trucks display vertically along the left side of the screen along with their servicing capabilities.

Color Legend

Routes

  • Blue - indicates the route is Scheduled.

  • Yellow - indicates the route is In Progress.

  • Green - indicates the route is Serviced.

Re-Assign Trucks

Click the route to open the Edit Route Record popup editor to reassign a truck. Save when finished

.

Related Articles:

Worker Availability and Capability